With the financing securely in place for
both the construction of the Seawall and the subsequent grade-raising,
construction commenced on the first phase of the plan devised by the Board of
Engineers. The wall against the sea would begin at the intersection of 8th Street
and the Harbor, run south to the Gulf, then curve gently toward the west and
run continuously from there to 39th
Street.
Thus
in preparation, four sets of railroad tracks were laid along this proposed
route in order to facilitate the delivery of materials to the work sites. In
just under two years this short stretch of track would convey 5,200 loads of
crushed granite, 1,800 loads of sand, 3,700 loads of granite riprap, 4,000
loads of wooden sheet pilings, and 1,000 loads of
concrete.
On
October 27, 1902, the first piling was driven into place at 16th Street, and the Seawall’s
foundation would be completed in its entirety before construction on the upper
portion began.
Per
the board’s instructions, the foundation measured sixteen feet wide and
consisted of a total of seven parallel rows of pilings that would be driven
into the ground along the line of the future wall. Four of these rows, set
three and a half feet apart, consisted of round piles made of Texas
yellow pine from Beaumont,
each approximately one foot across and 42 feet long.
Behind
the row of pilings closest to the beach side, three tight rows of 24-foot
planks were also put in place by the pile driver to reinforce round pilings and
to help prevent the undermining of the wall. Each piece of piling, whether
round or rectangular, took roughly twenty minutes to drive into place.
Four
machines manned by ten men apiece worked continuously and only stopped when
either the dark or the weather prevented it. Other workers followed behind the
pile drivers and dug three-foot trenches around the pilings which were then
filled with concrete made from a mixture of crushed granite, cement, sand, and
water.
Massive
cement mixers were placed on platforms with wheeled feet that bridged the
sixteen foot span of the foundation. They were then manually pushed along the
foundation to efficiently deposit the concrete directly into the trenches
below.
While
the foundation was nearing completion, loads of granite riprap began to arrive
from a quarry west of Austin,
over 200 miles away. The instructions for selecting the granite were specific:
one-fifth were to weigh in excess of 1,000 pounds, and at least half were
required to weigh a minimum of 200 pounds, and they were to be placed along the
toe of the Seawall to form an apron of rock between the wall and the beach.
Once
the Seawall was complete the riprap would diminish the force of the waves on
the wall and prevent the erosion of the beaches, but in the meantime it was
used to anchor the wooden structures that would frame the upper portion of the
wall.
Rising
seventeen feet above the foundation with a concave face, this upper portion was
the final step in the construction of the Seawall. Large wooden forms in the
shape of the wall were hammered into place and steadied by beams braced against
the large pieces of granite riprap, then they were filled with concrete.
The
concrete mixer used for the upper portion of the wall was more than twice the
size of the mixer used for the foundation, it even towered above the seventeen
foot frame. Two mechanical arms stretched out from either side of the mixer-
one arm moved the ingredients of the concrete from the railcars into the mixer,
and the other arm swung the other direction toward the wall, dumping the fresh
concrete into the frame.
Since
the concrete took seven days to dry, and in an effort to prevent damage as the
concrete settled, the upper wall was built sixty feet at a time, with
tongue-and-groove joints built into the interior of each section to reinforce
their connection. Working at a rate of one section per day, seven alternating,
sixty-foot sections were completed at a time, and then workers would backtrack
and fill in the ones in between.
This
method of construction was also implemented to ensure the future integrity of
the wall, making it flexible and giving it the ability to absorb the natural
contractions and expansions that were bound to occur over time.
The
original portion of the Seawall was completed on July 29, 1904, a mere
twenty-one months from the day construction began. It extended nearly eighteen
thousand feet, or just under three and a half miles, and it weighed an
estimated forty thousand pounds per foot. Almost immediately upon completion it
became a Galveston
attraction all of its own, as people were eager to promenade along the
magnificent sidewalk.
But
even before the first person took an elevated stroll along the Gulf shoreline, Galveston had already
come face to face with the impending reality of step two, the grade-raising.
There was no turning back now; without elevating the grade Galveston was effectively inside of a bowl
and any significant storm surge would be even deadlier than the one that
inspired the wall’s construction.
The Island’s
position on the water was more vulnerable than ever, and the ingenuity and
genius it was going to take to finish this task had yet to be discovered.